slava.energy: UK renewable energy projects
Belle Eau Park
REPD record 4879. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.9 MW
- Status
- Planning Permission Expired
- Operator
- Solar Choice
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Newark and Sherwood
- Planning reference
- 14/01782/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-08-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-10-07: Planning Application Submitted
- 2015-01-13: Planning Permission Granted
- 2018-01-13: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4879. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.