Allt na Moine
REPD record 489. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Small Hydro
- Capacity
- 2 MW
- Status
- Under Construction
- Operator
- RWE Npower Renewables & Innogy
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Highland
- Planning reference
- 14/00150/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-12-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-01-16: Planning Application Submitted
- 2014-07-28: Planning Permission Granted
- 2021-05-01: Under Construction
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 489. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.