Land North East Of Penrose Far
REPD record 4929. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.5 MW
- Status
- Operational
- Operator
- Clean Earth Energy
- County
- Cornwall
- Region
- South West
- Country
- England
- Planning authority
- Cornwall
- Planning reference
- PA14/12025
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-12-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-01-19: Planning Application Submitted
- 2015-05-15: Planning Permission Granted
- 2015-09-25: Operational
- 2018-05-15: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4929. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.