slava.energy: UK renewable energy projects
Capel Grange Solar Park
REPD record 4936. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.6 MW
- Status
- Operational
- Operator
- West Coast Energy
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Tunbridge Wells
- Planning reference
- 14/506168/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-06-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-12-12: Planning Application Submitted
- 2015-04-10: Planning Permission Granted
- 2015-11-01: Under Construction
- 2016-03-31: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4936. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.