Langwell Estate hydro scheme
REPD record 494. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Small Hydro
- Capacity
- 1.2 MW
- Status
- Operational
- Operator
- DHG Hydro
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Highland
- Planning reference
- 14/00371/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-01-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-01-29: Planning Application Submitted
- 2014-08-22: Planning Permission Granted
- 2015-06-15: Under Construction
- 2016-12-15: Operational
- 2019-08-22: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 494. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.