320mts South East of 43 Flush Road
REPD record 4953. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 2 MW
- Status
- Planning Permission Expired
- Operator
- Hill Power
- County
- Co. Antrim
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Belfast
- Planning reference
- Z/2014/1553/F
- Turbines
- 1
- Turbine size
- 2 MW
- Record last updated in REPD
- 2020-08-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-11-20: Planning Application Submitted
- 2015-03-26: Appeal Lodged
- 2015-11-04: Appeal Granted
- 2015-11-04: Planning Permission Granted
- 2020-11-04: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4953. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.