Former Maghaberry Airfield
REPD record 4954. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 25.7 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- Co. Armagh
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Lisburn and Castlereagh
- Planning reference
- S/2014/0913/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-04-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-01-14: Planning Application Submitted
- 2016-04-26: Planning Permission Granted
- 2017-09-21: Under Construction
- 2018-01-30: Operational
- 2021-04-25: Planning Permission Expired
Open this area on the map