slava.energy: UK renewable energy projects
Vantage Point Business Park
REPD record 4960. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.6 MW
- Status
- Planning Permission Refused
- Operator
- Bee Green Solar
- County
- Gloucestershire
- Region
- South West
- Country
- England
- Planning authority
- Forest of Dean
- Planning reference
- P1957/14/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-03-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-01-15: Planning Application Submitted
- 2015-03-16: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4960. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.