Independent Quarries
REPD record 5021. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3 MW
- Status
- Abandoned
- Operator
- The Crown Estate and Albion Stone
- County
- Dorset
- Region
- South West
- Country
- England
- Planning authority
- Dorset
- Planning reference
- WP/15/00039/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-12-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-02-16: Planning Application Submitted
- 2015-09-30: Planning Permission Granted
- 2027-09-30: Planning Permission Expired