slava.energy: UK renewable energy projects
Braevallich
REPD record 503. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Small Hydro
- Capacity
- 2.2 MW
- Status
- Operational
- Operator
- Innogy
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Argyll and Bute
- Planning reference
- 02/01407/GDCON
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2007-05-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2002-08-07: Planning Application Submitted
- 2003-03-26: Planning Permission Granted
- 2005-01-01: Operational
- 2017-03-26: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 503. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.