slava.energy: UK renewable energy projects
Land at Barrow Green Farm
REPD record 5058. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Planning Permission Refused
- Operator
- Dowsett Mayhew Planning Partnership
- County
- Surrey
- Region
- South East
- Country
- England
- Planning authority
- Tandridge
- Planning reference
- 2015/57
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-04-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-01-13: Planning Application Submitted
- 2015-02-25: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5058. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.