slava.energy: UK renewable energy projects
Lackford Landfill Scheme
REPD record 508. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 1.2 MW
- Status
- Operational
- Operator
- Gengas Ltd
- County
- Suffolk
- Region
- Eastern
- Country
- England
- Planning authority
- West Suffolk
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2004-09-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 1999-08-24: Planning Application Submitted
- 1999-11-02: Planning Permission Granted
- 2000-04-12: Operational
- 2014-11-02: Planning Permission Expired
Open this area on the map