slava.energy: UK renewable energy projects
Eveley Farm
REPD record 5080. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49 MW
- Status
- Operational
- Operator
- PS Renewables
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Test Valley
- Planning reference
- 15/00094/FULLS
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-03-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-02-16: Planning Application Submitted
- 2015-07-27: Planning Permission Granted
- 2016-03-01: Under Construction
- 2016-03-17: Operational
- 2018-07-27: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5080. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.