slava.energy: UK renewable energy projects
Land at Thornborough Grounds
REPD record 5092. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- NESF (formerly Lark Energy)
- County
- Buckinghamshire
- Region
- South East
- Country
- England
- Planning authority
- Buckinghamshire
- Planning reference
- 15/00723/APP
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-07-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-03-11: Planning Application Submitted
- 2015-06-10: Planning Permission Granted
- 2016-01-11: Under Construction
- 2016-03-31: Operational
- 2018-06-10: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5092. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.