Southern Counties Shooting Ground Phase 1
REPD record 5096. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 9 MW
- Status
- Operational
- Operator
- British Solar Renewables & NextEenrgy Solar Fund (NESF)
- County
- Dorset
- Region
- South West
- Country
- England
- Planning authority
- Dorset
- Planning reference
- WD/D/14/003367
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-03-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-12-24: Planning Application Submitted
- 2015-09-08: Planning Permission Granted
- 2016-09-15: Under Construction
- 2017-01-06: Operational
- 2018-09-08: Planning Permission Expired
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5096. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.