Home Farm
REPD record 5104. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3 MW
- Status
- Operational
- Operator
- Cenin Renewables
- County
- Vale of Glamorgan
- Region
- Wales
- Country
- Wales
- Planning authority
- Vale of Glamorgan
- Planning reference
- 2015/00852/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-06-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-07-30: Planning Application Submitted
- 2016-01-14: Planning Permission Granted
- 2017-01-09: Under Construction
- 2017-04-15: Operational
- 2021-01-14: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5104. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.