Elstow Landfill Site
REPD record 511. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 1.8 MW
- Status
- Operational
- Operator
- Renewable Power Generation Ltd
- County
- Bedfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- Bedford
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2003-12-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 1995-01-09: Planning Application Submitted
- 1995-06-23: Planning Permission Granted
- 1996-07-08: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 511. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.