Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Anesco
- County
- Derbyshire
- Region
- East Midlands
- Country
- England
- Planning authority
- North East Derbyshire
- Planning reference
- 15/00218/FL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-03-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-03-10: Planning Application Submitted
- 2015-06-25: Planning Permission Granted
- 2015-06-30: Under Construction
- 2015-09-30: Operational
- 2018-06-25: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5128. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.