Tower Hayes Farm
REPD record 5168. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Elgar Middleton
- County
- Leicestershire
- Region
- East Midlands
- Country
- England
- Planning authority
- Hinckley and Bosworth
- Planning reference
- 15/00343/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-08-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-03-20: Planning Application Submitted
- 2015-07-10: Planning Permission Granted
- 2016-01-17: Under Construction
- 2016-05-17: Operational
- 2018-07-10: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5168. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.