Lowther Hills (North Lowther Energy Initiative)
REPD record 5181. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 147 MW
- Status
- Appeal Refused
- Operator
- Forsa (formerly 2020 Renewables& Buccleuch)
- County
- Dumfries and Galloway
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- ECU00000426
- Turbines
- 30
- Turbine size
- 4.2 MW
- Record last updated in REPD
- 2021-07-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-06-12: Planning Application Submitted
- 2018-12-07: Appeal Lodged
- 2021-01-08: Planning Permission Refused
- 2023-01-08: Appeal Refused
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5181. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.