Hesta Head Wind Farm
REPD record 5198. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 20.4 MW
- Status
- Appeal Granted
- Operator
- Hoolan Energy& Hesta Head Wind Farm
- County
- Orkney Islands
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Orkney Islands
- Planning reference
- 17/083/TPPMAJ
- Turbines
- 5
- Turbine size
- 4 MW
- Record last updated in REPD
- 2020-08-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-03-06: Planning Application Submitted
- 2018-09-21: Planning Permission Refused
- 2018-10-08: Appeal Lodged
- 2019-04-18: Appeal Granted
- 2019-04-18: Planning Permission Granted
- 2027-04-11: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5198. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.