Millerhill EfW
REPD record 5247. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- EfW Incineration
- Capacity
- 12.5 MW
- Status
- Operational
- Operator
- FCC Environment
- County
- Midlothian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Midlothian
- Planning reference
- 15/00285/DPP
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-05-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-09-17: Planning Permission Expired
- 2015-03-31: Planning Application Submitted
- 2015-09-17: Planning Permission Granted
- 2016-10-06: Under Construction
- 2019-05-01: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5247. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.