slava.energy: UK renewable energy projects
Land at Beech Farm
REPD record 5253. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.6 MW
- Status
- Operational
- Operator
- Vortex (formerly SunEdison)
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Swindon
- Planning reference
- S/LDO/15/1133
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-07-06: Planning Application Submitted
- 2015-08-28: Planning Permission Granted
- 2016-02-17: Operational
- 2016-05-01: Under Construction
- 2018-08-28: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5253. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.