Hoplass Farm
REPD record 5257. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10 MW
- Status
- Operational
- Operator
- Kronos Solar
- County
- Pembrokeshire
- Region
- Wales
- Country
- Wales
- Planning authority
- Pembrokeshire
- Planning reference
- 12/1000/PA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-09-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-02-06: Planning Application Submitted
- 2014-04-16: Planning Permission Granted
- 2015-01-01: Under Construction
- 2015-03-13: Operational
- 2017-04-16: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5257. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.