slava.energy: UK renewable energy projects
Land At Chiddinglye Farm
REPD record 5263. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- REPOWER Balcombe & Chiddinglye Solar Park
- County
- West Sussex
- Region
- South East
- Country
- England
- Planning authority
- Mid Sussex
- Planning reference
- DM/15/2460
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-06-17: Planning Application Submitted
- 2015-09-30: Planning Permission Granted
- 2015-12-30: Under Construction
- 2016-03-30: Operational
- 2018-09-30: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5263. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.