Land East Of Honeysome Road
REPD record 5302. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.6 MW
- Status
- Operational
- Operator
- Honeysome Road Solar
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- Fenland
- Planning reference
- F/YR15/0429/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-04-25
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-05-20: Planning Application Submitted
- 2015-12-14: Planning Permission Granted
- 2016-03-15: Operational
- 2018-12-14: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5302. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.