Staining Wood Farm
REPD record 5328. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.9 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- Lancashire
- Region
- North West
- Country
- England
- Planning authority
- Fylde
- Planning reference
- 15/0337
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-08-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-05-18: Planning Application Submitted
- 2015-09-29: Planning Permission Expired
- 2015-09-30: Planning Permission Granted
- 2016-01-04: Under Construction
- 2016-03-30: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5328. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.