Land at Moss Farm (South)
REPD record 5329. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Planning Permission Expired
- Operator
- TGC Renewables/NESF
- County
- Cheshire
- Region
- North West
- Country
- England
- Planning authority
- Cheshire East
- Planning reference
- 15/2126N
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-09-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-05-08: Planning Application Submitted
- 2016-05-31: Planning Permission Granted
- 2019-05-31: Planning Permission Expired
Open this area on the map