slava.energy: UK renewable energy projects
Land between Orton Park Farm
REPD record 5330. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.4 MW
- Status
- Operational
- Operator
- INRG Solar
- County
- Cumbria
- Region
- North West
- Country
- England
- Planning authority
- Cumberland
- Planning reference
- 15/0405
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-03-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-05-11: Planning Application Submitted
- 2015-09-23: Planning Permission Granted
- 2016-01-22: Under Construction
- 2016-03-29: Operational
- 2018-09-23: Planning Permission Expired