Site To North East Of, Lochcraigs Farm
REPD record 5332. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- SBC Renewables
- County
- Ayrshire
- Region
- Scotland
- Country
- Scotland
- Planning authority
- North Ayrshire
- Planning reference
- 15/00252/PP
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-11-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-05-12: Planning Application Submitted
- 2015-08-13: Planning Permission Granted
- 2016-10-15: Under Construction
- 2017-03-31: Operational
- 2018-08-13: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5332. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.