slava.energy: UK renewable energy projects
Land at Sunnyside Court
REPD record 5334. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.9 MW
- Status
- Planning Permission Refused
- Operator
- Ethical Power
- County
- Derbyshire
- Region
- East Midlands
- Country
- England
- Planning authority
- South Derbyshire
- Planning reference
- 9/2015/0124
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-01-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-05-06: Planning Application Submitted
- 2015-12-16: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5334. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.