Green Croft Solar Farm
REPD record 5380. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Anesco
- County
- County Durham
- Region
- North East
- Country
- England
- Planning authority
- County Durham
- Planning reference
- DM/15/02279/FPA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-11-04: Planning Permission Expired
- 2015-07-23: Planning Application Submitted
- 2015-11-04: Planning Permission Granted
- 2016-10-07: Under Construction
- 2016-12-07: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5380. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.