slava.energy: UK renewable energy projects
Ernesettle Solar Farm
REPD record 5395. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.1 MW
- Status
- Operational
- Operator
- PEC Renewables
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- Plymouth
- Planning reference
- 15/01377/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-05-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-07-22: Planning Application Submitted
- 2015-09-25: Planning Permission Granted
- 2016-01-11: Under Construction
- 2016-03-23: Operational
- 2018-09-25: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5395. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.