Land At Pullen Farm
REPD record 5427. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10 MW
- Status
- Appeal Refused
- Operator
- Novus Solar Developments
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Tunbridge Wells
- Planning reference
- 15/503884/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-09-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-06-30: Planning Application Submitted
- 2016-03-24: Planning Permission Refused
- 2016-12-16: Appeal Lodged
- 2017-08-25: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5427. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.