slava.energy: UK renewable energy projects
Frog's Loke Solar Farm
REPD record 5430. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Frogs Loke Solar
- County
- Norfolk
- Region
- Eastern
- Country
- England
- Planning authority
- North Norfolk
- Planning reference
- PF/15/0938
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-07-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-06-26: Planning Application Submitted
- 2015-10-16: Planning Permission Granted
- 2015-11-16: Under Construction
- 2016-01-12: Operational
- 2018-10-16: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5430. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.