Clandeboye Estate Solar Farm
REPD record 5439. Status: Planning Application Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10.9 MW
- Status
- Planning Application Withdrawn
- Operator
- Hadstone Energy
- County
- Co. Down
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Ards and North Down
- Planning reference
- LA06/2015/0389/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-10-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-07-06: Planning Application Submitted
- 2016-09-15: Planning Application Withdrawn
Position not held by REPD.