slava.energy: UK renewable energy projects
South Antrim Solar Park - Phase 1
REPD record 5450. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.5 MW
- Status
- Operational
- Operator
- Hadstone Energy
- County
- Co. Antrim
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Antrim and Newtownabbey
- Planning reference
- LA03/2015/0262/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-01-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-06-30: Planning Application Submitted
- 2016-04-26: Planning Permission Granted
- 2018-03-10: Under Construction
- 2018-05-10: Operational
- 2021-04-25: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5450. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.