slava.energy: UK renewable energy projects
Bryncoch Solar Farm
REPD record 5462. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 19 MW
- Status
- Abandoned
- Operator
- Green Energy UK Direct
- County
- Carmarthenshire
- Region
- Wales
- Country
- Wales
- Planning authority
- Carmarthenshire
- Planning reference
- W/32171
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-10-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-06-15: Planning Application Submitted
- 2015-09-11: Planning Permission Granted
- 2020-09-11: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5462. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.