slava.energy: UK renewable energy projects
Jamesfield Solar Farm
REPD record 5471. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Planning Permission Expired
- Operator
- Green Power Consultants
- County
- Perth and Kinross
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Perth and Kinross
- Planning reference
- 15/00833/FLL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-09-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-06-17: Planning Application Submitted
- 2015-08-14: Planning Permission Granted
- 2018-08-14: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5471. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.