slava.energy: UK renewable energy projects
Churchers Common Solar Park
REPD record 5475. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Abandoned
- Operator
- British Solar Renewables
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Test Valley
- Planning reference
- 15/01399/FULLS
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-10-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-06-19: Planning Application Submitted
- 2015-12-01: Planning Permission Granted
- 2018-12-01: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5475. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.