Cwm Derwyn Farm
REPD record 5477. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Kronos Solar
- County
- Vale of Glamorgan
- Region
- Wales
- Country
- Wales
- Planning authority
- Vale of Glamorgan
- Planning reference
- 2015/00632/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-03-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-09-04: Planning Permission Expired
- 2015-06-01: Planning Application Submitted
- 2015-09-04: Planning Permission Granted
- 2017-01-15: Under Construction
- 2017-03-17: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5477. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.