Clapton Farm Solar Park
REPD record 5508. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- British Solar Renewables
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 15/03373/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-06-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-07-23: Planning Application Submitted
- 2015-11-17: Planning Permission Granted
- 2017-01-20: Under Construction
- 2017-03-31: Operational
- 2018-11-17: Planning Permission Expired