slava.energy: UK renewable energy projects
Rhas Fach Farm
REPD record 5517. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.2 MW
- Status
- Planning Permission Expired
- Operator
- Power for Wales Inc
- County
- Carmarthenshire
- Region
- Wales
- Country
- Wales
- Planning authority
- Carmarthenshire
- Planning reference
- W/32377
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-08-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-07-22: Planning Application Submitted
- 2015-09-30: Planning Permission Granted
- 2020-09-30: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5517. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.