slava.energy: UK renewable energy projects
Common Farm
REPD record 5527. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.8 MW
- Status
- Operational
- Operator
- Public Power Solutions& Swindon Borough Council
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Swindon
- Planning reference
- S/LDO/15/1247
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-07-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-07-29: Planning Application Submitted
- 2015-10-13: Planning Permission Granted
- 2016-05-02: Under Construction
- 2016-06-29: Operational
- 2018-10-13: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5527. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.