Pistyllgwyn Farm
REPD record 5571. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.5 MW
- Status
- Planning Permission Expired
- Operator
- Power for Wales Inc
- County
- Carmarthenshire
- Region
- Wales
- Country
- Wales
- Planning authority
- Carmarthenshire
- Planning reference
- W/32460
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-08-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-08-06: Planning Application Submitted
- 2015-12-21: Planning Permission Granted
- 2020-12-21: Planning Permission Expired