slava.energy: UK renewable energy projects
Corporation Farm
REPD record 5579. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Abandoned
- Operator
- Lightsource Renewable Energy
- County
- Essex
- Region
- Eastern
- Country
- England
- Planning authority
- Maldon
- Planning reference
- 15/00779/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-03-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-08-05: Planning Application Submitted
- 2015-11-30: Planning Permission Refused
- 2016-06-30: Appeal Lodged
- 2017-04-25: Appeal Granted
- 2017-04-25: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5579. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.