Land West of Parsonage Wood
REPD record 5582. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.2 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- Torridge
- Planning reference
- 1/0754/2015/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-05-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-08-05: Planning Application Submitted
- 2015-09-30: Planning Permission Granted
- 2016-01-31: Operational
- 2016-12-06: Under Construction
- 2018-09-30: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5582. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.