slava.energy: UK renewable energy projects
Port of Barry - Site 2
REPD record 5605. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Associated British Ports (ABP)
- County
- Vale of Glamorgan
- Region
- Wales
- Country
- Wales
- Planning authority
- Vale of Glamorgan
- Planning reference
- 2015/00173/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-10-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-02-18: Planning Application Submitted
- 2015-01-15: Under Construction
- 2015-04-15: Planning Permission Granted
- 2015-04-16: Operational
- 2020-04-15: Planning Permission Expired
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5605. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.