Mynydd Y Gwrhyd Windfarm
REPD record 5624. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 4.7 MW
- Status
- Revised
- Operator
- Awel Aman Tawe Community Energy
- County
- Neath Port Talbot
- Region
- Wales
- Country
- Wales
- Planning authority
- Neath Port Talbot
- Planning reference
- P2007/1413
- Turbines
- 2
- Turbine size
- 2.35 MW
- Record last updated in REPD
- 2015-10-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2007-09-20: Planning Application Submitted
- 2008-06-17: Planning Permission Refused
- 2008-12-15: Appeal Lodged
- 2009-05-07: Appeal Granted
- 2009-05-07: Planning Permission Granted
- 2014-05-07: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5624. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.