slava.energy: UK renewable energy projects
Daventry
REPD record 5639. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 1 MW
- Status
- Operational
- Operator
- Earthworm Energy
- County
- Northamptonshire
- Region
- East Midlands
- Country
- England
- Planning authority
- West Northamptonshire
- Planning reference
- DA/2015/0798
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-06-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-09-28: Planning Permission Expired
- 2015-08-20: Planning Application Submitted
- 2015-09-28: Planning Permission Granted
- 2016-10-17: Under Construction
- 2018-04-15: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5639. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.